- Home
- Departments
- Engineering
- Capital Projects
- Town of Clayton Water Reclamation Program
Town of Clayton Water Reclamation Program
The Town of Clayton is making significant strides in enhancing our wastewater infrastructure through the most extensive project in our history. Currently, construction is underway on various project components, with an anticipated completion timeline spanning the next three years. Broadly, the construction process encompasses a range of activities, including surveying, vegetation removal, stringent environmental controls, earthwork, precise concrete work, the assembly of facility components, the arrival of substantial equipment, electrical installations, rigorous testing, commissioning procedures, and ultimately, the meticulous restoration of the site.
This construction effort will be carried out in carefulyy planned phases for each program component, potentially allowing som activities to proceed concurrently or in a dynamic iterative fashin, contiengent on thier respective locations. Assisting the town in this ambitious endevaor is HDR, serving as a dedicated project advisor.
For more detailed information, we invite you to get in touch with our town staff via email at WRFinfo@townofclaytonnc.org.
- Sam's Branch Water Reclamation Facility (WRF)
- Little Creek Wastewater Transmission Improvements
- Little Creek Wastewater Pump Station
- East Clayton Industrial Area (ECIA) Pump Station and Force Main Improvements
- Capacity Expansion for the Clayton-to-Raleigh Pump Station
This facility, currently under construction, will be capable of treating six (6) million gallons of wastewater per day (MGD) of residential, commercial, and industrial flows. The facility is being built on a Town-owned site near the Neuse River at 1698 N O'Neil Street. The site is already home to other wastewater infrastructure. Thalle Construction Company is the general contractor; they have mobilized and started construction. Gannett Fleming is the Town's engineer of record.
Update - June 1, 2023
The transmission improvements, currently under construction, includes the installation of a new 24-inch force main from the existing Little Creek Water Reclamation Facility to the gravity discharge on Front St. The project includes bore and jacks under US-70, Front Street, and the NCRR railroad tracks. In addition, the project includes the installation of a new 24 to 48-inch gravity sewer from Front Street to the future influent pump station for the Sam's Branch WRF. JF Wilkerson is the general contractor. Withers & Ravenel is the Town's engineer of record.
This project component, currently under construction, includes a new pump station with a capacity of 13 MGD to divert flows from the existing Little Creek Water Reclamation Facility to the new Sam's Branch WRF. The new pump station will include submersible pumps, odor control, a standby generator, and a control building. Haren is the general contractor. Withers & Ravenel is the Town's engineer of record.
This ECIA project component, currently under final design and permitting, includes increasing the ECIA pump station capacity to 5 MGD and the installation of a new 20-inch force main to convey flow to the Sam's Branch WRF. A team of McKim & Creed - Withers & Ravenel is the Town's engineer of record.
This project component, currently under final design and permitting, includes expanding the Clayton-to-Raleigh pump station to convey a portion of the Town's raw wastewater flow to the City of Raleigh's Neuse River Resource Recovery Facility. This pump station is located directly adjacent to the Sam's Branch WRF site. The capacity expansion will allow the Town to fully utilize its contractual treatment capacity with the City of Raleigh and manage wastewater flows until the Sam's Branch WRF comes online. HDR is the Town's engineer of record.
-
Joshua Baird, PE, CFM
Engineering DirectorPhone: 919-553-1554
-
Jonathan K. Jacobs, PE, CFM
Assistant Engineering DirectorPhone: 919-553-1554
-
Engineering
Physical Address
111 E Second Street
Clayton, NC 27520
Phone: 919-553-5002